Rural Electrification Projects

1 - REHABILITATION AND REINFORCEMENT OF THE MAPUTO CITY DISTRICBUTION NETWORK - LOTE 1.

CONSULTANT: Sweco International

CONTRACTOR: EFACEC

VALIDITY OF THE CONTRACT: December,  2014

The Project is financed by the Portuguese Fund and is valued at 23 million Euros.

Description of the Project

Ø  The project consists of the rehabilitation and extension of the Jardim substation to 66/33/11kV,40MVA , anticipate that they will end in August 2014; 

Ø  Construction of a new substation at Costa do Sol of 66/33 and 33/11kV, 40 MVA, its completion is scheduled for Jun/14; 

Ø  Construction of a new substation in Zimpeto of 66/33 and 33/11kV, 40MVA. The "cold commissioning" is being fueled provisionally by the former DL5. 

Ø  Construction of a new substation in Marracuene of 66/33kV, 20MVA. Completed and energized. Building of the Medium Voltage lines is under way to interconnect the Substation with existing lines. 

Ø  Rehabilitation of the switching station PS1 and PS10. Completed the "cold commissioning" and PSs begin operating in late November, 2013. 

 

2 . CONSTRUCTIONOF THE 66Kv TRANSPORT POWER LINES  IN MAPUTO 

 

CONSULTANT: Sweco International

CONTRACTOR: Electrotec

DATE OF CONTRACT: December 2014

The Project is funded by the Electricity of Mozambique , EP worth 214 Million MT

Project Description

Ø  Construction of the Infulene – Zimpeto line, already finalizing the opening of foundations (80 %), raising the towers (77 %)  and equipment of the towers (60 %).

Ø  Construction of the Zimpeto – Marracuene line. The opening of foundations is underway (70 %), raising of the towers (63 % ) and equipment of the towers (63 % ),

Ø  Construction of the line SE9 - SE C. Sol. Opening of foundations underway (80 %), raising the towers (70%) and equipment of the towers (60 %).   

3. REHABILITATION AND REINFORCEMENT OF THE CUAMBA DISTRIBUTION NEWTORK  - ADDENDA 4 

Consultant: SWECO/COWI 

Contractor: ELTEL

VALIDITY OF THE CONTRACT:  31 December, 2014

Project is financed by SIDA and is valued at 48.1 Million SEK

Project Description

Ø  Construction of 50km of 33kV MV network, 70 km network of BT and the assembly of 37 PTs and connection of 2,700 new consumers. Effective contract since October 2013. Underway is the design of the project and mobilization of the contractor to the construction site, which is scheduled for completion in December, 2014 

 

4. MECULA RURAL ELECTRIFICATION 

CONSULTANT: NA 

CONTRACTOR: MPI

VALIDITY OF THE CONTRACT: By August, 2014 

The Project if financed by the Government of Mozambique and is valued at 123 Million Meticais. 


Project Description

Ø  Construction of 152km line of 33KV between Marrupa - Mecula and 20 km of BT network to 0.4/0.23 kV; 12 new PTs and connection of 1,000 new consumers. All poles of the MV line are adequately equipped and deployed, with work to launch conductors underway  (80 % already launched)

This project has its end in December 2014

 

 5. PROJECT ELECTRICITY III – Package  1 & 2  

CONSULTANT: Simon como e   A. Milice 

CONTRACTOR: SETHY, Portugal

VALIDITY OF THE CONTRACT: July, 2014

The Project is financed by ADB/OPEC  and is valued at 12 Million US dollars  

 

Ø  Construction of the Chidenguele - Chissibuca; Lindela -  Jangamo Beaches; Inharrime - Zavora MT lines; 

 

Ø  Construction of the - Namialo Nacaroa; Nametil - Chalaua; Rapale - Mecuburi MT lines, and 

Ø  BT Network and Link to 7,035 new customers. 

All lines are now energized or electrified 

 

6. ELECTRICITY IV PROJECT-LOTE 1 

 

FINANCIERS: BAD –OPEC-GdM            CONSULTOR:  EDF 

CONTRACTOR: NCC 

VALIDITY OF THE CONTRACT: 34 MONTHS – Dec. 2014 

The Project is financed by the ADB, OPEC and the Government of Mozambique and is valued at 21 Million US de Dollars. 

Project Description

Ø  Extension of 220 kV Chibata Substation

Ø  Rehabilitation of Lamego Substation; Mafambisse Substation

Ø  Construction of the New 220/110 and 110/33/22 kV Dondo Substation;

Ø  Construction of 167 km of Chibata-Dondo 220 kV line

Ø   Repositioning of 110 kV lines (Beira - 1 and Beira 2) on Arrival at the Dondo substation ( 5km)


Civil construction works are underway at the Lamego and Chibata Substation.

7. ELECTRICITY IV PROJECT-LOTE  3 

CONSULTANTEDF 

CONTRACTOR: EFACEC  

VALIDITY OF THE CONTRACT: 24 MONTHS – December, 2014

The Project is financed by the ADB, OPEC and the Government of Mozambique and is valued at 11.7 million US dollars.  

Project Description

Ø  Construction of the Dondo – Mwanza 33 kV line 

Ø  Construction of crossing Macossa - Macossa33 kV line 

Ø  Construction of the 33 kV line to Marringue 

Ø  Construction of the 33 kV line to Tambara 


Clearing the routes of distribution lines completed;
 

 

8. EXTENSION OF THE MATAMBO SUBESTATION 

CONSULTANT:    At selection phase  

CONTRACTORNCC from Saudi Arabia 

VAL. OF THE CONTRACT: 18 MONTHS – Dec. 2014 

The Project is financed by IDA and is valued at 11.0 Million US dollars. 

Project Description

Ø  Supply and assembly of the 130/100/30MVA, 220/66/33kV second Tansformador in th Matambo substation, including all control system, command and protection, installation of the SCADA and interconnecting the substations of Tete and Matambo.

 

9. CHIMUARA-NAMIALO-NACALA PHEASIBILITY STUDY 

FINANCIERS: NORAD     CONSULTOR:  NORCONSULT 

CONTRACTOR: N/A         VALUE:  MUSD 2.0

VALIDITY OF THE CONTRACT: August, 2013 

Project Description

Ø  Feasibility study for the construction of the Chimuara-Namialo-Nacala line

Technical report completed and submitted. The Impact of the Socio- Environmental study submitted to MICOA, now awaiting MICOA’s approval.

10. EXTENSION AND REINFORCEMENT OF THE NATIONAL TRANSPORT NETWORK  (MIXED CREDIT) 

CONSULTANT:  NORCONSULT/VPC 

CONTRACTOR: N/A  

VALIDITY OF CONTRACT:  60Months

The Project is financed by the Government of Mozambique and DANIDA and is valued at 144.6 Million Euros

Project Description

Ø  Provision of a 400MVA  400/275KV transformer; 

Ø  Construction of the 275 Ressano Garcia – Macia line; 

Ø  Construction of 110KV Lindela – Massinga line a nd 30MVAMassinga Substation; 

Ø  Provision of the 2nd transformer in Chimuara, Quelimane, Alto-Molocue and Central Nampula; 

Financing agreements signed in May 2013; 

The works contract approved by CREE in October; 

Advanced payment is expected for the kick-off of the works.

 

11. ELECTRIFICATION OF SOFALA, MANICA AND TETE (LOTE B – Tete Extension)  

CONSULTANT: VPC/NORCONSULT 

CONTRACTOR: n/a

VALIDITY OF THE CONTRACT: n/a

The Project is financed by SIDA and is valued at 46 Million SEKs 

Project Description

• Construction of 0.8 km of 66 and 33kV dual airline;

• Construction of 19 Km of the 33kV Medium Voltage line;

• Construction of 50Km of the 0.4kv Low Voltage network; PTs

• Connection to 2,200 consumers


Approval of the Report Evaluation by SIDA is pending and so is the homologation of the contract by MF consultancy, and the mobilization of the contractor is expected in early 2014.

12. ELECTRIFICATION OF THE SOFALA, MANICA AND TETE (LOTE B – Mobile Subestation)  

FINANCIERS: NORAD/SIDA

CONSULTANT: VPC/NORCONSULT 

CONTRACTOR: ETDE

VALIDITY OF THE CONTRACT: 12 Months (May, 2014) 

VALUE:  MSEK (14.824)

 

Project Description

 

Ø  Provision of a 66/33kV, 20MVA Mobile Substation to reinforce the Tete electricity network Tete.

Manufacture of SE Mobile is underway;

It’s expected to arrive in Mozambique in Feb/2014